As part of the pavement maintenance program, the 2021 Full and Partial Depth Asphalt Patching project consists of 3,914 square yards of full depth pavement repair and 17,515 square yards of partial depth pavement repair. Staff evaluated all city streets with a pavement condition index below 30. These targeted repairs to the existing pavement will address necessary structural restoration for isolated areas, leaving the remaining structurally sound pavement intact. This project includes mobilization, manhole reconstruction, and all appurtenant work for the completion of the project.
There were 2 construction bids for the project:
Base Bid Alternate 1 Base + Alt
Superior Bowen $ 598,1330.00 $66,000.00 $664,330.00
Ideker Inc. $ 859,885.80 $111,375.00 $971,260.00
Engineer’s estimate $ 781,270.00 $99,003.00 $880,793.00
Superior Bowen has completed various asphalt projects successfully and timely for the City in the past. Their base bid and add alternate bid is the lowest and below the engineer’s estimate, therefore their bid is being recommended for this contract.