Council action is requested to authorize the City Manager to approve a construction contract with Legacy Underground Construction, Inc. for an amount not to exceed $708,290 authorizing future minor change orders not to exceed $70,829 and/or time extensions for the 2023 Neighborhood Sanitary Sewer Project (No. 302004-1).
Recommendations:

Council approval is recommended. 
Executive Summary:

There were 4 construction bids for this project.

 

Legacy Underground Construction, Inc.: $708,290

Linaweaver Construction, Inc.: $790,485

Infrastructure Solutions, LLC: $835,475

SHEDIGS IT, LLC: $895,344

 

City Staff have verified references from neighboring municipalities for Legacy Underground Construction, Inc. Their bid is being recommended for approval of this contract.

 

This is a budgeted capital project. 

 

Background:

City Staff have identified 3 areas of concern with existing and/or potentially serious issues within the gravity sanitary sewer system which will be addressed by this construction project. These locations are at Blue Ridge Terrace south of 23rd Street, W 24 Street S. east of S. Crysler Avenue, and Mill Creek Park.



Fiscal Impact:

The fiscal impact to the City is $779,119 including contingency. Funding for the Neighborhood Sanitary Sewer Projects (No. 302004) is included in the FY 24 adopted budget, page number 182, account number 7030-5406.

Department:          Municipal ServicesContact Person:          Lisa Reynolds


REVIEWERS:
DepartmentAction
Public Works DepartmentApproved
Finance DepartmentApproved
City Managers OfficeApproved
City Clerk DepartmentApproved

Council Action:          Council Action:         

ATTACHMENTS:
DescriptionType
Official Bid Tabulation Summary #23096 - 2023 Neighborhood Sanitary Sewer Project No. 302004Exhibit